Oś czasu

PROJECT START
Milestones
Deliverable products

09/2021

11/2021 – Project website

2022

02/2022 – L-1 building techical report (WUST site)

08/2022 – New refrigerant blend selected and fully tested.

08/2022 – New refrigerant selection report

2023

02/2023 – PV system ready STES technical report

05/2023 – EPCM determination for the STES Innovative cooling device running flawlessly (WUST stie)

05/2023 – Demonstration installation final design EPCM selection report

2024

05/2024 – COOLSPACES4LIFE project movie

08/2024 – EPCM determination for the STES Innovative cooling device running flawlessly (UAL stie)

08/2024 – Solar cooling device report Environmental and socio- economic impacts assessment report No. 1

2025

2026

07/2026 – LCA/LCC report

02/2026 – Meetings with key stakeholders

08/2026 – Environmental and socio- economic impacts assessment reports No. 2 Business plan License package Replication plan Report on proactive means taken

08/2026

PROJECT END